Media Manager status meeting 2.2.2017
By Allon Moritz on 2017-02-03 05:53 in New Media Manager Team
Thursday 2th February 2017 on Google Hangouts
Time: 19:30 CEST
List of Attendees Overview
Attendee |
A |
A |
|||
Allon Moritz (Lead) |
CH |
x |
|||
Marco Dings |
NL |
||||
Yves Hoppe |
DE |
x |
|||
David Neukirchen |
DE |
x |
|||
Dawn Russell |
US |
||||
Britta Stender |
DK |
||||
Ufuk Avcu |
DE |
||||
Dimitris Grammatiko |
GR |
x |
|||
Jisse Reitsma |
NL |
||||
Other Attendees: |
na |
||||
David Steadson |
SE |
x |
|||
To-dos
Name |
Responsible |
Status |
Image manipulation research |
Yves |
|
List view PR |
David |
|
Drag and drop |
Dimitris |
|
UI Mockups - Angular Integration |
Britta - Dawn |
General topics
UX/UI
Some design examples can be seen in the slides from the UX team
Some examples are shown below:
An interactive link is on https://projects.invisionapp.com/share/5WA1VK8HU#/screens.
Survey status:
-
10 questions will be asked
-
Survey will be probably expanded with questions about the edit view
-
Expected date is on 6. February when all is going well
Milestone
We were discussing if milestone 1 should be in Joomla 4 or 3.8. No decision is made.
PR List view
PR list feature is needed till next week, otherwise we need to make a new plan for milestone 1, because it will be hard then to reach the delivery date. After the List PR is done, we will contact some community members personally to get their opinions about the vue.js approach.
Dev Topics:
-
After a bit of research from Allon. Multipart related is too advanced for such a simple use case we have in the media manager. So Dimitris, Yves, David and Allon decided to try base64 encoding upload for milestone 1.